The Herbert mills crushed about 202,000 tonnes of cane for the week, taking the season total to just over 859,000 tonnes.

Victoria Mill undertook a 12-hour A-side maintenance stop on Tuesday and Macknade Mill had a 12-hour maintenance stop on Thursday.

There was a slight increase of 0.34 of a unit in CCS levels on the previous week. The season-to-date CCS is tracking below the budgeted 12.9 units.

Victoria Mill will have a planned 12-hour B-side mill cleaning intermission on Wednesday 4 August.

Locomotive crews have reported early morning visibility conditions due to fog.

Motorists and harvesting contractors are urged to take caution while these conditions prevail.

Lindsay Wheeler
Cane Supply Manager
Herbert Region